MassDEP Response to Comment concerning
NRG Canal 3 Development LLC
350 megawatt simple cycle turbine
August 4, 2017
Page 13 of 15
NRG requests that MassDEP remove the particulate testing requirement at MECL from the AQPA
and PSD Permit.
The proposed AQPA requires testing for NO
x
, CO, VOC, NH
3
and opacity at MECL, 75% and 100%
load on each fuel. In addition, the proposed PSD permit requires testing for NO
x
at MECL, 75% and
100% load on each fuel. For NO
x
, CO, VOC, NH
3
, and opacity, NRG believes the 75% load
performance testing requirement is unnecessary. Performance testing at MECL and 100% load will
be sufficient to ensure the facility design is adequate to ensure compliance across the steady-state
load range. In addition, NO
x
, CO, and NH
3
will have continuous emissions monitoring systems
(CEMS) to continually determine continuous compliance at all loads.
NRG requests that MassDEP remove the 75% load testing requirement for NO
x
, CO, VOC, NH
3
, and
opacity from our proposed AQPA, and remove the 75% load testing requirement for NO
x
from the
PSD Permit. (NRG)
MassDEP Response to Comment 15:
The NSPS Subpart KKKK at 40 CFR 60.4400 (b) states “The performance test must be done at any
load condition within plus or minus 25 percent of 100 percent of peak load. You may perform testing
at the highest achievable load point, if at least 75 percent of peak load cannot be achieved in practice.
You must conduct three separate test runs for each performance test. The minimum time per run is 20
minutes.” Accordingly, the NSPS only requires one test, consisting of 3 runs and is specific to NOx.
Testing for the additional pollutants is required by the Department to ensure compliance with the
established emission limits, i.e. BACT.
In evaluating this request with respect to NO
x
and CO, the Department considered the predicted
impacts at the various loads as determined by the emissions modeling conducted for the Project. The
“worst-case” scenario relative to the unit’s impact on the NAAQS occurs either when the unit is firing
at 100% of its rated capacity, has an hour with startup transitioning to 100% load, or is operating at
minimum load. For these cases, the total impact on the ambient atmosphere (including background
and existing Canal Station sources) will be 70% of the 1-hour NO
2
NAAQS, 25% of the annual NO
2
NAAQS and less than 20% of both the 1-hr and 8-hr CO NAAQS. 75% load is not the worst case
load for any pollutant/averaging period combination. For VOC and NH
3
, VOC is not subject to
dispersion modeling, and NH
3
has predicted impacts of 1% of the MassDEP air toxics guideline limit.
Therefore, MassDEP agrees to remove the 75% load testing requirement for NO
x
, NH
3
, CO and
VOC. Moreover, NO
x
, NH
3
and CO will each have a certified continuous emission monitoring
system (CEMS), which will provide continuous “direct-compliance” data to determine compliance
with allowable limits at any actual operating load. In addition, the Plan Approval requires the
Permittee to establish a VOC/CO correlation curve for purposes of continuously assessing VOC
compliance. Therefore, MassDEP agrees that a performance test at MECL and 100% load for NO
x
,
NH
3
, CO and VOC will provide sufficient documentation of compliance for NSPS Subpart KKKK
and the AQPA/PSD limits.
With respect to particulates (PM/PM
10
/PM
2.5
), MassDEP agrees to remove the testing requirement at
MECL. MassDEP has considered the point made by the Applicant that the same lb/hr value is the
controlling emission limit at all steady state loads on each fuel. This is based on the manufacturer’s
guarantee for particulate emissions. Therefore, it is expected that the controlling case for particulate
emission compliance will be 100% load, when a greater amount of fuel is being fired compared to